Bridge over St. Croix hobbled by delays; opening postponed again - Bring Me The News

Bridge over St. Croix hobbled by delays; opening postponed again

Author:
Publish date:
Image placeholder title

Advocates for a new Stillwater-area bridge over the St. Croix River have been waiting for decades – what's another year?

A combination of factors that have slowed the project led transportation officials to push back the opening of the bridge to the fall of next year, which is a full year later than originally planned.

According to the Stillwater Gazette, the transportation departments of Minnesota and Wisconsin said in a joint announcement that those factors have included shortages of workers and materials, problems with equipment and the weather, and the complexity of the project.

https://twitter.com/PioneerPress/status/684941740797767680

The states had already said that a 2016 opening would not happen. While they've now pushed the opening into late 2017, MnDot project director Michael Beer offered no new target date for an opening – only reassurances that the revised timeframe is "well within the project team's capability to meet," the Gazette says.

The Pioneer Press notes the delay has implications for the contractor building the bridge. Lunda/Ames Joint Venture stood to gain millions of dollars in incentive payments if certain targets were met. Beer tells the newspaper discussions underway with the contractor are looking at the causes of the delays and whether the contract should be modified.

The St. Croix Crossing project

The St. Croix between Minnesota and Wisconsin is a National Scenic River. For years, environmental and recreational groups fought construction of the bridge in court, arguing it violated federal protections.

But the transportation departments of both states argued the span connecting Oak Park Heights, Minnesota, and Houlton, Wisconsin, is needed to safely move the growing number of travelers crossing the river. They ultimately won the fight, although the design of the bridge was modified to minimize its impact on the river valley's scenery.

Construction of the 3,200 foot bridge started in 2013. The cost of the project is budgeted at up to $646 million.

Find more background, including the bridge's design and a webcam showing the construction work at MnDot's St. Croix Crossing web page.

Next Up

Related

MnDOT: Construction on new St. Croix River bridge to begin next spring

MnDOT officials tell MPR that foundation work on the new bridge crossing the St. Croix River downstream from Stillwater will begin next spring, rather than in 2014. The proposed four-lane bridge connecting Minnesota and Wisconsin will replace the 80-year-old Stillwater Lift Bridge. The entire project is estimated to cost up to $676 million and take about three years to complete.

New St. Croix River bridge sails through Senate

The U.S. Senate unanimously authorized construction of a new St. Croix River bridge near Stillwater. The move comes after 15 years of debate over how to improve traffic flow while also protecting the St. Croix, which is a National Scenic River.

U.S. House set to vote on St. Croix River bridge

Supporters of a new bridge near Stillwater have been pushing the concept for decades. They believe they can finally reach their goal if the House votes to exempt part of the St. Croix from its status as a Wild and Scenic River. But the bridge has its critics. They're using financial arguments in hopes of rallying opposition.