Court overrules Goodhue County plan to block wind farm

The Minnesota Court of Appeals has overturned a Goodhue County ordinance that would have prevented construction of a 50-turbine wind farm. But the project remains on hold until the developer comes up with a plan to protect eagles and other birds.
Author:
Updated:
Original:

The Minnesota Court of Appeals has overturned a Goodhue County ordinance that would have prevented construction of a 50-turbine wind farm. But the project remains on hold until the developer comes up with a plan to protect eagles and other birds.

Next Up

Twin Cities Pride 3

Twin Cities Pride is going ahead in July this year – but no parade

The in-person event will be held in Loring Park in Minneapolis.

Screen Shot 2021-05-14 at 12.27.58 PM

Rejuvenation, Williams-Sonoma's furniture brand, to open first MN location

It is moving into the former Restoration Hardware unit at the Galleria in Edina.

police lights

Charges: Driver pulled alongside, shot at motorist on I-35

The man is charged with second-degree assault.

classroom

7th Minnesota school employee dies from COVID-19

The death was confirmed by the health department.

duluth lighthouse

Want a lighthouse? The U.S. Coast Guard is giving one away in Duluth

Federal, state and local agencies, as well as some nonprofits are eligible to take over the lighthouses for free.

Pexels - newborn baby blanket

Henry continues its run as MN's most popular baby name

The state's 100 most popular baby names were revealed this week.

Related

Plan for wind farm shelved to protect migrating birds

The Public Utilities Commission dealt a setback to a planned wind farm near Red Wing. Commissioners decided the plan does not do enough to protect eagles and other birds that could be killed by its 50 turbines. The decision will at least delay the project and could kill it.

Some Goodhue County landowners want to get out of wind turbine contracts

Several landowners have sent letters of termination to AWA Goodhue Wind. One of their concerns is the possible effect the turbines could have on wildlife. One Rochester resident says the turbines could disrupt the flight paths of migratory eagles and endanger the birds.

New wind farm could face big fines if turbines kill eagles

The Fish and Wildlife Service is advising AWA Goodhue Wind to apply for a permit that would reduce its liability if any eagles are killed by the spinning turbines of its planned wind farm. Without a permit, a second offense could cost the company half-a-million dollars.

PUC postpones hearing on controversial wind farm

Goodhue Wind plans to apply for a permit from the U.S. Fish and Wildlife Service that would allow its turbines to kill eagles without facing penalties. The proposed 48-turbine site is set to be located north of Zumbrota in southeast Minnesota. MPR reports the hearing with the Minnesota Public Utilities Commission has not been rescheduled.

Wind farm seeking permission to kill eagles near Red Wing

Developers of a controversial wind farm in Goodhue County plan to apply for new federal permits to legally kill eagles. The Star Tribune reports the permits are part of a federal compromise between the demand for clean energy and the concern that wind farms could kill thousands of birds each year. The proposed 50-turbine site near Red Wing is home to a number of eagles and endangered golden eagles.

Faribault County’s first commercial wind farm to add 60 local jobs

Construction on the 36-megawatt Big Blue Wind Farm in Blue Earth is already underway. The 18 new wind turbines being installed feature nacelle enhancements and a more aerodynamic blade design that optimizes energy output -- enough to power about 20,000 homes per year. The south-central Minnesota wind farm is scheduled to be operating by the end of the year.

Wind farm developer accuses residents of attracting eagles to halt project

The developer of a 50-turbine wind farm says Goodhue County residents are leaving animal carcasses out to attract eagles. The presence of eagles could affect the project. State officials have not verified the accusations.

Central Minnesota wind farm a year behind schedule

The necessary permits are in place to build a 95-megawatt wind farm north of Paynesville, but Edina-based Geronimo Wind Energy is still looking for a utility company to buy its energy. A St. Cloud Times report says this has delayed construction by a year on central Minnesota's first large-scale wind farm, that includes as many as 60 turbines.