Crews finish sliding new Larpenteur Avenue Bridge into place

Author:
Publish date:
Image placeholder title

After unexpected delays that extended the operation by a day, Minnesota Department of Transportation crews finished sliding the new Larpenteur Avenue Bridge over I-35E into place early Friday, FOX 9 reports.

The 3.5 million-pound bridge deck (and its beams) were pushed into place with hydraulic jacks using a new "slide-in" technique. The structure was originally planned to be in place by early Thursday morning, but construction crews hit a snag about halfway through the process.

KSTP says the delay was caused by metal bending in places it wasn't supposed to.

The Star Tribune says crews completed the job about 2 a.m. Friday. State bridge engineer Nancy Daubenberger told the newspaper the remainder of the project went well "after adjustments were made to the location of the guide plates on the slide tables."

See a time-lapse video of the Larpenteur Avenue Bridge operation below.

States like Oregon, Utah, Missouri, Michigan, Colorado and Massachusetts have previously employed the slide-in technique, but the Larpenteur Bridge project marks the first time the method's been used in Minnesota, the Star Tribune reports. The bridge was reportedly constructed about four feet from where the previous structure existed.

MnDOT says the big plus for using the technique comes with the amount of time – and money – saved on construction.

“Doing this bridge under conventional methods, the closure would be about 110 days,” project manager Dave Herzog told KSTP. “With the method we’re using here, we’re going to get it completed and open in about 47 days.”

Herzog says the bridge will open again in about three weeks, after additional work is completed.

Next Up

Related

Crowds gawk as new Hastings bridge is maneuvered into place

A state transportation official compared it to parallel parking a 6.5 million pound piece of equipment. Barges floated the main span of a new Hastings bridge down the Mississippi River and maneuvered it into place over the weekend. The span had been assembled upstream. It now sits alongside the existing bridge. There's more work to be done before it opens to traffic next spring.

State-of-the-art technology wheels in new bridge

Crews with the Minnesota Department of Transportation used a "self-propelled modular transporter" for the first time to move the Maryland Avenue bridge over Interstate 35E Saturday. Kent Barnard with MnDOT tells KARE 11 the new technology reduced closure time for the bridge deck by 50 percent.

Futuristic bridge construction: Giant robotic belt to place finished span

The Maryland Avenue Bridge over Interstate 35E just north of downtown St. Paul is coming down beginning July 13. The street will be closed until early or mid-September, when it reopens with a new bridge in place. Workers are building the new bridge at a nearby site, and in what might signal the future of bridge construction, a giant robotic conveyor belt will roll the span into place during a 12-hour window over two weekends in August.

Crowd gathers for reopening of Lowry Avenue bridge

More than 350 people gathered in the metro Saturday for the reopening of the Lowry Avenue bridge, which connects north and northeast Minneapolis, The unveiling of the $104 million project was marked with parade, jet flyover and water ski show.