Updated:
Original:

Sabo bridge closure costs more than $1.1M

Officials with the city of Minneapolis, Hennepin County and the Met Council told Minnesota Public Radio the cost to shutdown and repair the pedestrian and bicycle crossing topped $1.1 million. The Sabo Bridge was closed for three-and-a-half months after two of the bridge's supporting cables came loose in February. A report released in June blames the failure on wind vibrations.
Author:

Officials with the city of Minneapolis, Hennepin County and the Met Council told Minnesota Public Radio the cost to shutdown and repair the pedestrian and bicycle crossing topped $1.1 million. The Sabo Bridge was closed for three-and-a-half months after two of the bridge's supporting cables came loose in February. A report released in June blames the failure on wind vibrations.

Next Up

ISSAboveYou - Duluth North Shore - Oct 18 2021

Watch: Mille Lacs, Duluth captured in stunning video from ISS

The space station provides a vantage point 260 miles above the Earth's surface.

2048px-The_Weeknd_with_hand_in_the_air_performing_live_in_Hong_Kong_in_November_2018

Ladies and gentlemen, The Weeknd has canceled his St. Paul show

He's made changes to his 2022 tour that involves scrapping his Xcel Energy Center gig.

Pixabay - police lights, tape

Man released from custody after admitting to fatal shooting in ND

Authorities said there is no threat to the public.

rochester-water-tower

MN water tower in the running for Tank of the Year

It was the only water tank to receive more than 5,000 votes.

first snow

Any sign of snow in the forecast for Minnesota?

The stars could align for some flurries in northern Minnesota this week, but that's about it.

Flickr - 14 year old vaccine shot - Navy Medicine

Walz announces $200 reward for kids 12-17 who get COVID shots

Those ages have the lowest vaccination rates among all eligible age groups.

Screen Shot 2021-10-15 at 10.01.55 PM

Police still searching for suspect who opened fire at Plymouth movie theater

It sparked a partial evacuation of the Emagine Willow Creek theater.

covid, vaccine

Minnesota's COVID-19 update for Monday, October 18

Hospitalizations have surpassed 1,000 in the latest update.

Related

Report: Wind to blame for Sabo Bridge failure

Hennepin County and the city of Minneapolis released this press release Friday. In short, a preliminary report suggests that wind is to blame for the failure of two cable connections on the Martin Olav Sabo pedestrian and biking bridge in Minneapolis. The bridge was closed from Feb. 19 to June 1.

Sabo Bridge could reopen by June

Officials say that Minneapolis is striving to reopen the Martin Olav Sabo Bridge by June 4, the Star Tribune reports. The bicycle and pedestrian span over Hiawatha Avenue has been closed for three months, after the fracture of a steel anchor led the bridge’s tallest set of cables to fall from the mast on Feb 19.

Sabo bridge reopens to bikes, pedestrians

The Sabo bridge, which was closed after a pair of support cables broke in February, is reopening Friday afternoon to foot and bike traffic. Structural support was added underneath the bridge deck. Minneapolis is awaiting a report on what caused the cables to break loose.

Sabo reopens Friday until next repair phase

Workers installed a retrofitted diaphragm plate on the Sabo pedestrian bridge this week and the bridge reopened Friday morning, at least until more repairs are done to finish the project. Engineers will then plan and schedule repairs to the rest of the bridge’s diaphragm plates later this year.

Minneapolis considers re-opening Sabo bridge during repairs

Crews are still working to stabilize the bike and pedestrian bridge and investigators are studying why a cable that supported the deck broke in February. But Minneapolis would like to reopen the span and hopes to find out soon if that would be safe.

Minneapolis will try to solve mystery of why Sabo bridge cable failed

City officials say it could take months to learn why one of the bridge's cables broke, shutting down traffic on the busy street and light rail track that run beneath it. The bike-and-pedestrian bridge is only five years old and had recently passed an inspection.

Sabo bridge plates had 'poor fatigue resistance'

Cable diaphragm plates that cracked on the Martin Olav Sabo Bridge, leading officials to shut down the span for months this year, had "welded details that offer poor fatigue resistance," according to a 140-page report released Friday by the city of Minneapolis.